Client: KfW, Germany and EPS - JP Elektroprivreda Srbije, Serbia
Name of partner(s): Tractebel Engineering GmbH (former Lahmeyer International), Germany
Start/Completion Date: November 2011-October 2021
Project description: After an operation time of almost sixty years the Zvornik Hydroelectric Power Plant on the Drina River needed rehabilitation. The purpose of the project "Rehabilitation of Hydroelectric Power Plant Zvornik (HPP Zvornik)"
Read more
Client: IFC - International Finance Corporation
Name of partner(s): N/A
Start/Completion Date: October 2017 - December 2017
Project description: The overall purpose of the Europe and Central Asia (ECA)
Read more
Client: KfW, Germany and EPCG - Elektroprivreda Crne Gore AD -Nikši?, Montenegro
Name of partner(s): Lahmeyer International GmbH, Germany - Main Contract holder
Start/Completion Date: May 2008 - October 2015
Project description: The Modernization and Rehabilitation of Perucica HPP-Phase II Project was
Read more
Client: Public Institution „Vode Srpske“ (Javna Ustanova „Vode Srpske“), Bosnia and Herzegovina
Name of partner(s): SAFEGE, Belgium - Main Contract holder
Start/Completion Date: October 2013-August 2015
Project description: The overall objective of the project was to support national and regional
Read more
Client: MWH International Inc. (financed by IFC)
Name of partner(s): N/A
Start/Completion Date: August 2010- September 2011
Project description: Technical Consultancy services in preparation of the proposals for the award of the right by concession for the project of development of hydropower plants for the purpose of utilizing the hydropower potential of the Mora?a River.
Read more
Client: RWE GmbH, Germany
Name of partner(s): N/A
Start/Completion Date: July 2010 - February 2011
Project description: This due diligence was aimed to review the existing studies for the pump storage power plant Djerdap III which dates back to the first technical documentation in 1973 and revisions and further investigations that were
Read more
Client: RWE GmbH, Germany
Name of partner(s): N/A
Start/Completion Date: May 2010 - November 2011
Project description: Almost the whole Velika Morava watershed, with an area of 37320 km2, is located in the territory of Serbia. Mean multiannual discharge of this river, which is 182 km long, equals to around 230 m3/s. Evaluation of the optimal
Read more
Client: PIROT ENERGO d.o.o, Serbia
Name of partner(s): N/A
Start/Completion Date: April 2009 - November 2009
Project description: SHPPs Pirot I-VII are unified cascade small hydropower plants on the stretch of the Nišava river, downstream of the HPP Pirot to the border with the municipality of Bela Palanka. Solution with cascading SHPPs was designed
Read more
Client: RWE GmbH, Germany
Name of partner(s): N/A
Start/Completion Date: March 2009 - May 2009
Project description: A due diligence of the four hydro power projects had been conducted. It was based on an engineering design (Feasibility Study), dating from February 2008. The due diligence was comprised of the following services:
Read more
Client: RWE GmbH, Germany
Name of partner(s): N/A
Start/Completion Date: January 2009 - February 2009
Project description: A due diligence of the two hydro power projects had been conducted. It was based on an engineering design (Preliminary Design), dating from February 2005. The due diligence was comprised of the following services:
Read more
Client: KfW, Germany and HET - Hidroelektrane na Trebišnjici, Bosnia and Herzegovina
Name of partner(s): Fichtner GmbH, Germany - Main Contract holder
Start/Completion Date: November 2005 - August 2009
Project description: The services covered technical assistance to HPP Trebinje 1 during equipment testing, tendering procedure and execution of works. Our experts were engaged in the estimation of condition of main mechanical and electrical
Read more
Client: Electric Power Industry of Montenegro (EPCG) AD - Nikši?, Montenegro
Name of partner(s): N/A
Start/Completion Date: October 2008 – March 2009
Project description: The study was performed sequentially in two phases: I PHASE - Based on the existing relevant data regarding daily flows recorded on water gauge stations Pernica, Zlatica and available topographic layouts of the watershed,
Read more
Client: Technor Energy AS, Norway
Name of partner(s): Institute for civil works IG, Banja Luka
Start/Completion Date: March 2008 – September 2008
Project description: Small hydro power plants Doboj, Cijevna 5 and Cijevna 6 are planned within integral project of development, protection and exploitation of the Bosna River course in the stretch between Doboj – Modrica, including also parts of
Read more
Client: La CardoImmobiliare S.r.l. , Italy
Name of partner(s): N/A
Start/Completion Date: March 2008 - August 2008
Project description: The aim of this study was to analyze river Sava hydro power potential, especially HPP Kupinski Kut and HPP Morava 1 to 6. As a result, recommendations and conclusions regarding realization of these projects were provided.
Read more
Client: PIROT ENERGO d.o.o, Serbia
Name of partner(s): N/A
Start/Completion Date: June 2007 - February 2008
Project description: In May 2007 SEEC contracted with the Municipality of Pirot preparation of Pre-feasibility Study for Optimization of Water Resources Management for the Nisava River Catchment’s Area. Main objective of the documentation was to
Read more
Client: Technor Energy AS, Norway
Name of partner(s): N/A
Start/Completion Date: March 2007 – August 2007
Project description: Objective of 4 Feasibility Studies for SHPP Cijevna 1, 2 3 and 4 was to select the optimum exploitation of hydropower potential of the Bosna River stretch, between Doboj-Modrica, and each structure within the power system.
Read more
Client: Private Investor
Name of partner(s): N/A
Start/Completion Date: November 2006 - February 2007
Project description: In November 2006 year SEEC contracted with a private investor Consultancy services in the process of privatization of five Small Hydro Power Plants (SHPP) in Montenegro. Contracted services were related to the following
Read more
Client: Technor Energy AS, Norway
Name of partner(s): N/A
Start/Completion Date: September 2006 - December 2006
Project description: This Pre-Feasibility Study had provided comprehensive information on the proposed technical solution and attractiveness of an investment into small hydropower plants Cijevna 1, Cijevna 2 and Cijevna 4 on Bosna River in
Read more
Client: Enel S.p.A, Italy
Name of partner(s): N/A
Start/Completion Date: May 2006 - July 2006
Project description: The purpose of consultancy services provided by SEEC experts were to analyze the possibilities for the construction of small hydro power plants in Serbia. This Report can be considered as an extension of The Pre-feasibility
Read more
Client: Italian Ministry for Environment and Territory, Italy
Name of partner(s): N/A
Start/Completion Date: February 2005 - August 2005
Project description: The main objectives of the study were based on review of existing documentation, relevant regulation, energy market requirements, environmental protection requirements and appropriate EU directives identification of
Read more