TPP Maritza East-1 (Bulgaria) Project Justification within SEE Power System, Bulgaria

Client: BNP Paribas and EBRD (AES Corporation)

Name of partner(s): N/A

Start/Completion Date: April 2005 - June 2005

Project description: Task of our experts was to perform due diligence services on behalf financing parties. The service included three tasks. First, based on the results of GIS project, least-cost expansion planning activities including updating of demand forecast, fuel cost data, economic, data etc. Second, revision of GIS least cost expansion plan considering TPP Maritza East 1 as candidate project competing with other regional candidate projects planned for (re)construction. Third, sensitivity analyses within South East Europe Regional Electricity Market. Work has been successfully finalized at the end of June 2005. Within this Study activities of SEEC included the following:

 

 




© Copyright S.E.E.C. Ltd. 2006-2025